When Will Massapoag Avenue Paving Be Completed?

Find out in this week's edition of You Ask . . . Patch Answers.

This week, Sharon Patch checked into the status of the paving project on Massapoag Avenue.

According to Sharon Superintendent of Public Works Eric Hooper, the binder, or initial layer, of pavement should be in the sidewalk by the end of this week, about Sept. 28.

The paving of the roadway should be completed by the end of next week, around Oct. 5, Hooper said, and the final layer of the sidewalk should be completed by Oct. 12.

Have a question about something that's happening in Sharon? Want to get the latest on a project in town or just curious about anything in general? You Ask … Patch Answers is a weekly column for locals looking for solutions to community problems, issues and those "only in Sharon" situations that you want solved. If you've got a question about something in Sharon, send it to sharonpatch@patch.com, and our team will dig up an answer.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something